Tuesday 12 August 2014

We have doors!

Our skirting, architraves and doors were installed today. The waterproofing is scheduled for tomorrow. Thankfully our SS managed to sort out an issue we had with the size of the bath and shower niches (which originally I thought would hold up the waterproofing) so we are still on track.

Kitchen and bathroom vanities have been scheduled for next Monday with wet area tiling to commence on Thursday.






Our front door


Internal doors


Shower niche (increased)